*Jordan Woods Natural Area -- community trail project

Bond Category:Trail Expansions
Site Address:Access on north end of 107th, north of Cornell
Portland OR 97229
Status:Completed
 
Master Plan Start:Summer 2009
Construction Start:Spring 2012
Construction Finish:March 2013
Estimated Public Opening:March 2013
Map | Directions | TriMet

Project Summary & Public Benefits

The master plan for this area includes the Jordan Woods Natural Area and Jackie Husen Park.

The Jordan Woods Natural Area Trail connects Lost Park Drive to 107th Avenue and Jackie Husen Park.

Jackie Husen Park is a neighborhood park with typical amenities like play equipment, pathways and open space areas. Jackie Husen Park opened in 2010, and was not funded by the 2008 bond.

The Jordan Woods Natural Area was funded by the 2008 bond. It is a linear community trail development project. Additional paved and soft surface trails, an overlook, two bridges and boardwalk will be installed to provide for complete site access.
 

Update

As always, if you have any comments and/or questions we would like to hear from you.  Please contact Melissa Remick via email, at 503/629-6305 or by using the THPRD Web contact form.

 

(Content updated 1-15-2015)  

Project Budget

$1,600,000

Contact Information

Please direct bond project-related comments or questions to Melissa Remick via email, at 503/629-6305 or electronically via THPRD's web contact form.

Contractor Information

Design Consultant:  Walker Macy

General Contractor:  Brant Construction



15707 SW Walker Rd, Beaverton, OR 97006