THPRD will hold a neighborhood meeting to discuss proposed upgrades to the play area at Hazeldale Park. Your attendance and comments are welcome.
Saturday, Sept. 23
9:00 a.m. - 10:00 a.m.
Hazeldale Park
SW 195th Ave & SW Farmington Rd, Aloha, OR 97007
Aloha, OR 97007
Chuck Gregory (AKS Engineering) and Jerry Burgess (THPRD) will discuss future park improvements including replacement of parking lot and playground equipment (currently 28-years old).
Neighbors can vote either at the park meeting or on our website for their favorite playground. Online voting will become available Sept. 23, 2017.
Online voting was completed October 12, 2017. Option 1 - Earth Tone is the winning design.
The project is a two-phase project.
Phase I
Design modification to add new playground location onto existing parking lot design and resubmit to County & CWS for approval and permitting.
Phase II
Construction July 1 through September 1, 2018. (Pending capital budget approval for 2018-19).