Barsotti Park
Bond Category:
Park Additions and Upgrades
Site Address:
16610 SW Blanton St Beaverton OR
Status:
Completed
Master Plan Start:
Spring 2012
Construction Start:
July 2013
Construction Finish:
December 2013
Estimated Public Opening:
January 2014
Barsotti Park opened to the public in January, 2014. The new neighborhood park has the district's first youth tennis court, designed for players age 10 and under. Other features include a multipurpose field that can accommodate baseball or softball as well as organized youth soccer and lacrosse activities.
The park’s most distinctive element is a viewing area behind the backstop featuring four large mounds. A hard-surface trail around the park’s perimeter weaves through these unique landforms to other amenities, including a covered picnic area, a 20-plot community garden (with four ADA-accessible plots), and a play area built on a resilient rubber surface. The play area includes separate sections for younger and older children.
Land for the park was purchased from the Barsotti family with funds from the 1994 bond measure. With the purchase, Park District can ensure the Barsotti family's desire to maintain the land as a gathering place for families for years to come.
Barsotti Park is located at 16610 SW Blanton St. in Aloha.
(Content updated 1-29-2015)
Project Summary & Public Benefits
The 2008 bond measure provided funds to fully develop the 3.75-acre Barsotti Park in Aloha, which THPRD acquired in 1996. Park design was based on public input, regulatory factors and park management needs. Initial ideas included a softball field, a multipurpose field, a loop trail, community gardens, play equipment and a community garden.
Project Budget
$1,250,000
Contact Information
Please direct bond project-related comments or questions to Nicole Paulsen via email or electronically via THPRD's web contact form.