ALERT: Summer Activities Guide is available online (click here to view). Print versions will be available in centers by March 21, 2024.
Elsie Stuhr Center
Bond Category:
Facility Rehabilitation
Site Address:
5550 SW Hall Blvd. Beaverton, OR OR 97005
Status:
Completed
Master Plan Start:
March 2009
Construction Start:
March 2012
Construction Finish:
March 2012
Estimated Public Opening:
May 2012
Project Summary & Public Benefits
The safety of our patrons is one of THPRD's highest concerns. That's why passage of the 2008 bond measure was so important - it allows the district to attend to important maintenance work and structural upgrades at a number of facilities.
Several upgrades have been made to the popular Elsie Stuhr Center, including structural upgrades for seismic stability. Other upgrades include enlarging the fitness room and entrance, and creating additional parking spaces and other amenities for vehicles, pedestrians and buses.
Improvements at the Stuhr Center were completed in March, 2012.
Project Budget
Contact Information
Please direct bond project-related comments or questions to Nicole Paulsen via email or electronically via THPRD's web contact form.