ALERT: Summer Activities Guide is available online (click here to view). Print versions will be available in centers by March 21, 2024.
Harman Swim Center
Bond Category:
Facility Rehabilitation
Site Address:
7300 SW Scholls Ferry Rd Beaverton, OR OR 97008
Status:
Completed
Master Plan Start:
April 2009
Construction Start:
January 2012
Construction Finish:
February 2012
Estimated Public Opening:
February 2012
Project Summary & Public Benefits
The safety of our patrons is one of THPRD's highest concerns. That's why passage of the 2008 bond measure was so important - it allows the district to attend to important maintenance work and structural upgrades at a number of facilities.
Structural improvements have been made to the Harman Swim Center to make it safer should an earthquake occur.
Project Budget
$73,115
Contact Information
Please direct bond project related comments or questions to Nicole Paulsen at 503/629-6305 or electronically via THPRD's web contact form.