Summercrest Park
Bond Category:
Natural Area Preservation
Site Address:
East of Rigert Road and 170th Beaverton OR 97007
Status:
Completed
Master Plan Start:
Spring 2009
Construction Start:
Summer 2010
Construction Finish:
April 2012
Estimated Public Opening:
April 2012
Habitat restoration work at this site is complete. In February 2012, THPRD staff installed 1,600 native trees and shrubs in Summercrest Park. To aid in the establishment of the new plantings, contractors continued work to control non-native vegetation through 2013.
Project Summary & Public Benefits
Natural area restoration at Summercrest Park included 1.5 acres of non-native trees, shrubs, and groundcover removal followed by replanting with native trees and shrubs.
Project Budget
$10,300
Contact Information
Please direct bond project-related comments or questions to Nicole Paulsen via email or electronically via THPRD's web contact form.