Sunset Swim Center - Seismic Upgrade
Bond Category:
Facility Rehabilitation
Site Address:
13707 NW Science Park Dr Portland, OR OR 97229
Status:
Completed
Master Plan Start:
April 2009
Construction Start:
June 2012
Construction Finish:
June 2012
Estimated Public Opening:
June, 2012
The Swim Center was closed in spring 2012 while the work was being performed. Swimmers were able to use the nearby Aquatic Center at 15707 SW Walker Road until the Sunset pool reopened in June, 2012.
Project Summary & Public Benefits
The safety of our patrons is one of THPRD's highest concerns. That's why passage of the 2008 bond measure was so important - it allowed the district to attend to important maintenance work and structural upgrades at a number of buildings.
The Sunset Swim Center was one of several THPRD facilities that needed structural improvements to make it safer in the event of an earthquake.
Seismic work at the Sunset Swim Center included reconstructing some of the internal walls and replacing a section of the roof. Exterior windows were added, as was a vestibule at the pool’s entry.
Project Budget
$625,225
Contact Information
Please direct bond project related comments or questions to Nicole Paulsen via email or electronically via THPRD's web contact form.