Tualatin Hills Athletic Center - HVAC
Bond Category:
Facility Rehabilitation
Site Address:
15707 SW Walker Rd Beaverton OR 97006
Status:
Completed
Master Plan Start:
May 2009
Construction Start:
November 2009
Construction Finish:
April 2010
Estimated Public Opening:
April 2010
Upgrades at the Tualatin Hills Athletic Center have improved air quality and the comfort and safety of our visitors, particularly during the summer.
The new system has expanded opportunities to schedule events, which might not have been otherwise practical during extreme summer heat.
An upgraded ventilation system was installed as was an upgraded control system. Supply and return chilled water lines were insulated, and new controllers were installed on the five air handler units. A new chiller unit was installed, and lines were connected from the chiller to the building.
Project Summary & Public Benefits
An upgraded ventilation system has been installed and the control system has been upgraded at the Tualatin Hills Athletic Center. The new system improves air quality and patron comfort and safety, particularly during the hot summer months.
The new system will expand opportunities to schedule events, which might not have been otherwise practical during extreme summer heat.
Project Budget
$500,000
Contact Information
Please direct bond project related comments or questions to Nicole Paulsen viaemailor electronically viaTHPRD's web contact form.